Summertime Construction Projects Planned across the District

Friday, June 3, 2016
images

Dozens of construction projects districtwide will be in full swing during the summer break.

From the repainting of schools and the installation of exterior lighting to repaving play courts to the relocation of portables, dozens of schools will have projects complete by the beginning of the 2016-17 academic year in August.

Changes at Addicott Elementary School over the summer are expected to be among the most dramatic. The school serves students with severe disabilities, including those who are orthopedically impaired, intellectually disabled, have multiple disabilities, are deaf and have other health impairments.

The $2.5 million project will include additional handicap accessible walkways, safety features, and expanded sensory walls and gross motor areas so students can expand their skills.

Campus/Project/Completion

Addicott: Modernization, August/2016

Bullard: Portable Replacement, June/2016

Robinson: Kindergarten Building Site Utility and Parking Lot, September/2016

Duncan: Gym Cooling, September/2016

Ericson: Exterior PA Speakers, July/2016

Fremont: Water Conservation Project, August/2016

Homan: Pave Play Courts, August/2016

Homan: Exterior PA Speakers, July/2016

Homan: Water Conversation, August/2016

Manchester GATE: Chiller Replacement, August/2016

McLane: Gym Cooling, August/2016

Roeding: Water conservation, August/2016

Thomas: Water conservation, August/2016

Phoenix Academy: Exterior public address speakers, July/2016

Roosevelt: Gym Cooling, September/2016

Exterior Painting: Baird, Birney, Bullard TALENT, Calwa, August/2016

Easterby, Ericson, Heaton, Jefferson, Lane, Norseman, Powers,

Thomas, Wilson, Wishon

Exterior Lighting: Ahwahnee, Baird, Edison Computech, October/2016

Cooper, Fort Miller, Kings Canyon, Scandinavian, Sequoia,

Tehipite, Tenaya, Terronez, Tioga, Wawona, Yosemite

Wolters Elementary - Exterior public address speakers, 7/2016